When applying for the net-metering, the distributed generation facility has to fulfil the following requirements according to NEPRA’s regulations

Arrange testing of grounding along with other related requirements by a licensed electrician

Make a formal written request to the concerned electrical inspector along with copy of the test report

Electrical inspector shall detail an individual from his office or visit himself for verification.

If satisfied, shall issue the NOC

If not satisfied, shall advise removal of faults /observations

After rectification, repeat the request and get NOC

The protection and control single line diagrams for the interconnection are to be provided by the Distributed Generator (DG) for commissioning of net-metering

As per NEPRA’s regulations, the grid-connected inverters shall comply with UL 1741 standard.

Other standards for the components are:

  1. IEEE 1547 2003
  2. IEC 61215
  3. EN or other international standards

For the DGs having an installed capacity of more than 500kW, load flow study (on PSSE software) is compulsory, and for the distributed generation facilities having a capacity less than 500kW, load flow study can be carried out using FDRANA.